Knowledgebase

Home > Knowledgebase > Cim50 > Planning > MRP > Actioning MRP Recommendations

Actioning MRP Recommendations

Actioning an MRP Recommendation is the process from which a recommendation to purchase or manufacture stock becomes a new purchase order or works order.

You can action a works order by highlighting one or more recommendations from the MRP Recommendations list view, and then selecting Process > ‘Action’.

Alternatively, you can also right click on a recommendation and select ‘Action’ from the right click menu.

Once you have the ‘Action’ screen open you are presented with 2 action points with several options:

Quantity to Action: This point will determine the quantity that will be used when generating the purchase/works order(s). There are 2 options available to select from:

Recommended Order Quantity: The quantity that the MRP process has recommended. This quantity is calculated based on the demand quantity and the MRP/Supplier order rules put in place on the relevant stock record.

Demand Quantity: The exact quantity required to satisfy the demand, regardless of any supplier/MRP rules in place on the relevant stock record.

You can see both the Recommended Order Quantity and the Demand Quantity values in the MRP Recommendations list view.

Associated Recommendations: This point determines which recommendations you wish to action. There are 4 options to select from:

Action Selected Recommendations Only: Action only the recommendations that were highlighted in the MRP Recommendations list when the ‘Action’ menu option was selected.

Action Selected Recommendations and ALL Descendants: Action the selected recommendations that were highlighted in the MRP Recommendations list when the ‘Action’ menu option was selected, plus any recommendations that were raised because of those recommendations being generated.

Action Selected Recommendations and MANUFACTURED Descendants: Action the selected recommendations that were highlighted in the MRP Recommendations list when the ‘Action’ menu option was selected, plus any manufacture recommendations that were raised as a result of those recommendations being generated.

Action Selected Recommendations and PURCHASED Descendants: Action the selected recommendations that were highlighted in the MRP Recommendations list when the ‘Action’ menu option was selected, plus any purchase recommendations that were raised as a result of those recommendations being generated.

 A descendant is a recommendation that has been generated because of another recommendation. For example, if we had a recommendation to raise a works order for 100 Maple Desks, that would also generate a demand to manufacture 100 Maple Drawsets, which would generate a demand to purchase 100 Lock Sets. Depending on stock and replenishment availability those demands generated for the Drawsets and Lock Sets may also generate a recommendation. If so, that recommendation would be a descendant of the recommendation for the Maple Desks.

To action the recommendation, press the OK button.

Note: If you are actioning a manufacture recommendation, depending on your works order settings you may be presented with a screen to define the works order numbers for the works orders that will be generated.

Similarly, you may also be presented with a screen where you can provision batch or serial numbers for the works orders being generated.

Once the action has completed, you will be returned to the MRP Recommendations list. The recommendations that were actioned will show a new status of ‘Actioned’. The recommendations will be highlighted in green in the list view, indicating they have been processed, and the ‘Order Reference’ column will display the Works Order or Purchase Order number that was generated from the recommendation.

Once a recommendation has been actioned, you will be unable to amend, combine, split, or action the recommendation.

Actioning a Reschedule Recommendation

In addition to the new purchase and manufacture recommendations described above, MRP can also raise recommendations to reschedule existing Works Orders earlier or later in time. These appear on a separate list view – the MRP Rescheduling list view – and can now be actioned directly from there to update the Works Order due date and re-schedule its operations automatically.

Reschedule recommendations are actioned using their own screen, which only offers the “Action Selected Recommendations Only” option. For full step-by-step instructions, see the Rescheduling article.

Please Note: Only Works Order reschedule recommendations can be actioned. Purchase Order reschedule recommendations remain view-only and will need to be amended on the Purchase Order in Sage 50.

Actioning a Service Recommendation

MRP can also raise recommendations to service a machine resource or a tooling resource, based on the service intervals set against the resource record. These appear on the new Servicing list view (see the Servicing article) and are actioned from there by highlighting one or more rows and choosing Process > Action, or by right-clicking a row and choosing Action.

The Action Service screen shows the reference of the resource you are servicing at the top, and contains the following fields:

Start date: The date and time the service started. This defaults to today’s date and time. Use the drop-down to amend if the service happened earlier (or later).

End date: The date and time the service finished. This defaults to today’s date and time. The End date must be on or after the Start date.

Notes (optional): Any free-text notes you wish to record alongside the service booking – for example, the parts that were replaced or any observations from the engineer who carried out the work.

To confirm the service and update the resource, press the Confirm button. To close the screen without recording anything, press the Cancel button.

When you press Confirm, Cim50 will do three things in one go:

  1. Create an ad-hoc booking in the Scheduler against the resource, with the Start date and End date you entered, using the Scheduler ad-hoc booking code that has been configured with a Type of “Service”. The description on the booking will read “Service: [Resource Reference]” and your notes will be saved against it.
  2. Update the Last Serviced field on the underlying resource record (the Machine Resource or Tooling Resource) to the End date you entered. This is the date MRP will use as the new baseline when working out when the resource is next due for service.
  3. Mark the corresponding service recommendation on the Servicing list view as “Actioned” so it no longer appears as outstanding work.

If multiple rows were selected on the Servicing list view, the Action Service screen will reopen for the next row after each Confirm, until every selected row has been processed. Pressing Cancel on any row stops the loop without affecting any rows you have already confirmed.